Case Studies
Cardinal Health
Project Scope
Cable new three story building, including:
- Cable approximately 2250 workstations and offices
- Design and build Server room
- Design and build IDF Rooms
Schedule
1st & 2nd Floor completed in 10 weeks, 3rd Floor completed in 10 weeks.
Critical Business Issue
- 1st & 2nd Floor Rough-In (Approximately 2100 cables) had to be installed within 3 weeks to coordinate with ceiling installation.
- 3rd Floor Rough-In (Approximately 2400 Cables) within 4 weeks to allow warehouse racking and shelving installation. Missed deadline would not allow future access to floor cores for modular furniture cabling.
- Large percentages of cables were going to be out of TIA/EIA-568-B.1 horizontal cabling specifications due to deficiencies in architectural engineering.
Capabilities
- BICSI ANSI/TIA/EIA Compliance Review
- Project Management
- Data Center Design
- Horizontal Cabling
Results
- Completed all phases on-time, within budget.
- All cables in ANSI/TIA/EIA compliance
USA Federal Credit Union
Project Scope
Run Outside Plant Cable (OSP) from building to building for an ATM Machine.
Schedule
1 Day
Critical Business Issue
Out of state ATM Vendor on-site for installation day only. No cable path known to get cable outside U.S. Navy base convenience store to neighboring building.
- Capabilities
- Project Management
- Situation Analysis / Engineering
- Horizontal Cabling
- BICSI ANSI/TIA/EIA Compliance Review
Results
- Identified optimum route for cable path
- Met one-day ATM Vendor schedule
- ATM installed on-schedule, within budget
L-3 Communications
Project Scope
Retro-fit conference table with power and data grommets.
Schedule
2 Days
Critical Business Issue
Conference table had single post legs with no cable path from the floor into table, no cable path from wall to table.
- Capabilities
- Custom Millwork
- Furniture Grommet Cuts
- Floor Coring
- Voice & Data Horizontal Cabling
- Corporate Move Services
- Electrician Services
Results
- Design and built custom table bases
- Core floor to accommodate cable path to table
- Cut Power/Data grommets in existing table
- Connected electrical outlets in core floor for Power/Data grommets